• someacnt_@lemmy.world
    link
    fedilink
    arrow-up
    2
    ·
    edit-2
    6 months ago

    I mean, it seems normal for big structure constructions to take 5 years at least…

    About bog standard construction, I meant not standardized nuclear, but that many parts of it is just constructions

    • frezik@midwest.social
      link
      fedilink
      arrow-up
      2
      arrow-down
      1
      ·
      6 months ago

      And 5 years is what nuclear projects have promised at the start over the years. Everyone involved knows this is a gross lie.

        • frezik@midwest.social
          link
          fedilink
          arrow-up
          2
          arrow-down
          1
          ·
          6 months ago

          China built a few Ap1000 designs. The Sanmen station started in 2009 with completion expected in 2014 (2015 for the second unit). It went into 2019. The second, Haiyang, went about the same.

          This is pretty similar to what happened in the US with Volgte.

          • someacnt_@lemmy.world
            link
            fedilink
            arrow-up
            2
            ·
            6 months ago

            Interesting, that was not what happened in my country. Sometimes it does take 8 years from allowance to finishing, but that’s it.